LOT 2, BINTAN INDUSTRIAL ESTATE
LOBAM, BINTAN, KEPULAUAN,
RIAU 29154, INDONESIA

Monday, September 27, 2010

Latest Update!



Two workshops (20m W x 120L each) have been completed. 
Each workshop is serviced by two units of SWL 20T overhead cranes 
and one unit of SWL 5T overhead crane.
 
 Construction of light jetty. Scheduled for completion by 1st week Oct 2010.


View from the security lookout platform.
Opposite is the Lobam Island.

 
 Equipment awaiting installation: lathes, milling machines,
 1000 Ton presses, shearing machine, plate rolling machine, etc.

 
 Commencement of steel fabrication