Monday, September 27, 2010

Latest Update!



Two workshops (20m W x 120L each) have been completed. 
Each workshop is serviced by two units of SWL 20T overhead cranes 
and one unit of SWL 5T overhead crane.
 
 Construction of light jetty. Scheduled for completion by 1st week Oct 2010.


View from the security lookout platform.
Opposite is the Lobam Island.

 
 Equipment awaiting installation: lathes, milling machines,
 1000 Ton presses, shearing machine, plate rolling machine, etc.

 
 Commencement of steel fabrication

Tuesday, July 6, 2010

Contract Award : Jacking Equipment for the Salvage of Rig "West Atlas"

Contracted by customer from Netherlands for the manufacturing of lifting clamps and strandjack support equipment (total : 250 tons)  for the salvage of damaged rig "West Atlas".  See http://en.wikipedia.org/wiki/Montara_oil_spill for information on the damage.  Contract will be performed in Singapore.

The damaged rig "West Atlas" in the Montara oil field
at the Timor Sea off the northern coast of Western Australia.
(http://www.rawfish.com.au/greens-senatordeplores-governments-west-atlas-oil-spill-management/ )

Latest Update!

Main columns, trusses and purlins have been erected. 
Getting ready for the roof & wall covering and installation of the 10-Ton overhead cranes.
 
The security post iwo beach & jetty.

 Finishing touch to the new electrical substation. 
Capacity: 2000KV

 New signage "SINGATAC OFFSHORE CENTRE" installed. 

The new foundation for the tower crane being
installed.  Total weight: approx. 300 tons.

 Getting the crane components ready for installation
in mid July 2010.








Friday, April 16, 2010

Ready......Get Set......Go! [Almost...]

 100m x 75m

Future PT MG's office.  Maybe.  I will consider.



An important chapter.

Friday, April 9, 2010

250T Transporter - The New Found Toy!!

Mr. Tai and his guys trying out the "new toy"!

BIE Newsletter

There is a feature in the Jan~Mar 2010 newsletter about PT Singatac Bintan.

Construction-In-Progress

Courtesy of Mr. K.S. Kang, we get following updates.

Workshop B - Production Floor Laid

Sub-Station
 
Production Toilet

Staff Canteen

Main Entrance Signage

 Main Access Road

 Foundation for Gantry Cranes