Main columns, trusses and purlins have been erected.
Getting ready for the roof & wall covering and installation of the 10-Ton overhead cranes.
The security post iwo beach & jetty.
Finishing touch to the new electrical substation.
Capacity: 2000KV
New signage "SINGATAC OFFSHORE CENTRE" installed.
The new foundation for the tower crane being
installed. Total weight: approx. 300 tons.
Getting the crane components ready for installation
in mid July 2010.